The Kitchen Remodel, Trade by Trade
Who shows up to a kitchen remodel, in what order, and why the plumber and the electrician each make two visits.

Lock the cabinet layout before anyone opens a wall, because Cabinet IQ of Huntsville says outlet heights, the sink drain and the gas line are all set from it, and changing it later means opening a wall again. For a homeowner that is the expensive kind of surprise: a reopened wall, a trade called back, a schedule that slips. It is also why the plumber and the electrician are the rare houseguests invited twice, and welcome both times.
The first visit happens while the room is still studs. The second happens once there is a sink to connect. Everything between is a trade waiting its turn.
Kitchen Remodel Order of Trades
Here is who comes, in order:
- Kitchen designer, and an architect if walls move. Block describes the designer as the person who shapes layout and function, and says an architect may be needed if walls move or structure changes. Designer Eva Bradley told Livingetc to bring in a designer and architect to set the kitchen's flow and concept before work begins. How a designer plans the layout is in Denise Benach on Kitchen Layout and the Work Triangle.
- General contractor. The project manager overseeing the timeline and the subcontractors, who should also handle permits and inspections.
- Demolition crew. Cabinets, counters, flooring and appliances come out, and plumbing and electrical connections are disconnected.
- Plumber and electrician, first visit. Circuits, outlets, supply lines and drains move to their final places.
- Drywaller and painter. They arrive after inspection passes, and only a first coat goes on, because touch-up is inevitable.
- Tile setter or flooring installer. Tile usually goes down before cabinets (more on that below).
- Cabinet installer. The boxes go in, set level.
- Countertop fabricator. Templating, then fabrication.
- Tile setter again, for the backsplash. What the tile setter does on the wall is in Kitchen Backsplash Tile.
- Plumber, electrician and appliance installers, second visit. Final connections, appliances and trim finish the room.
Why Plumbers and Electricians Come Twice
The first visit is rough-in, when circuits, outlets, supply lines and drains move into open walls, after which the layout is no longer adjustable. Hunker says to expect an electrician for most electrical work, and a plumber to move or add a water line or work on gas lines. Check appliance dimensions from the actual units before cabinets are ordered, since appliances often differ from their published measurements. Swapping a gas range for induction adds a circuit and a cap-off, covered in Gas to Induction Conversion.
In New York City the stakes are written into the process. Brick Underground reports that the Department of Buildings inspects plumbing and electrical work after demolition. A licensed plumber and electrician can self-certify, but a failed spot check means reopening walls and ends self-certification.
The second visit comes after cabinets and countertops. Cabinet IQ lists sink, dishwasher and disposal hookups, stove, hood and refrigerator connections, and wiring for lighting and outlets as that work. What to settle on the sink and faucet before rough-in is in Kitchen Sink Plumbing Renovation, the hood and its makeup air in Who to Hire to Install a Range Hood and Makeup Air, and the layers of light in Kitchen Lighting Plan With Dimmers and Under Cabinet Light.
Tile Before or After Cabinets
Sources differ a little on the floor. Cabinet IQ's second guide says flooring may go in before or after the cabinetry, while its Huntsville guide is more specific: tile usually goes down before cabinets, and some flooring is installed around cabinets afterward. Either choice changes cabinet height and toe kick.
The clearest rule comes from Cabinet IQ: set tile first, and decide on the floor before the cabinets are ordered, because the toe kick is built around it. Which kind of cabinet to order, and who builds it, is in Stock vs Semi-Custom vs Custom Kitchen Cabinets. Backsplash and wall tile follow the cabinets.
Who Hires the Trades and Files Permits
A general contractor manages the project, hires the trades and holds the schedule. The alternative is the homeowner coordinating specialists, which makes the homeowner responsible for the sequence. Hunker notes a homeowner can hire carpenters, drywallers, tilers and flooring installers directly, and Livingetc's experts recommend bidding the project with several general contractors.
Cabinet IQ says permits may be required for electrical, plumbing, structural and ventilation work, and that the contractor or project manager should handle permits and inspections.
What Demolition Can Uncover
Demolition is where water damage, mismatched wiring and unexpected plumbing tend to surface. Hunker advises that in houses built before 1980, suspect materials are tested for asbestos before the demo crew starts.
Kitchen Remodel Timeline
A full kitchen remodel averages 6 to 12 weeks once construction starts, according to Block, covering demo, rough-in, inspections, cabinets, countertops, flooring, painting and finishes. Permits or structural changes add time on top, as Eva Bradley told Livingetc. Where the money goes, line by line, is in Kitchen Remodel Cost Line by Line.
Kitchen Remodel Credits
Every trade on the job, in order of appearance: kitchen designer and architect, general contractor, demolition crew, plumber and electrician (rough-in), drywaller and painter, tile setter or flooring installer, cabinet installer, countertop fabricator, tile setter (backsplash), then plumber, electrician and appliance installers for the finish.
Countertops and the Final Visit
The countertop fabricator can only measure once the cabinets are in and level, and the sink and faucet have to be on site by then, because the cutouts follow the actual fixture. The fabricator's route from template to install day is in Countertop Fabrication Steps.
Only after that does the second visit start. The sink gets its hookups, the stove and hood their connections, the lights their wiring. Livingetc's Kasia Piorko puts that last stretch, plumbing and electrics connected and the kitchen finally usable, at about a week.
Every Kitchen Trade, One Page Each
- Kitchen Remodel Cost Line by Line: a sample budget, and the trade each line pays.
- Denise Benach on Kitchen Layout and the Work Triangle: how far apart the fridge, sink and range sit, and how wide the aisles are.
- Stock vs Semi-Custom vs Custom Kitchen Cabinets: stock, semi-custom and custom, and who builds and hangs each.
- Countertop Fabrication Steps: template to install day, then the stones side by side.
- Kitchen Backsplash Tile: what to choose, and the setter's work from center line to caulk.
- Kitchen Lighting Plan With Dimmers and Under Cabinet Light: each layer on its own dimmer, wired before the walls close.
- Who to Hire to Install a Range Hood and Makeup Air: sizing, ducting outside and makeup air.
- Gas to Induction Conversion: the circuit, the gas cap-off and the order the trades arrive.
- Kitchen Sink Plumbing Renovation: what to settle on the sink, faucet and appliances before rough-in.
Planning a coffee station too? Built-In Coffee Bar Planning Before the Walls Close settles it before the drywall.
Highlights
Why do the plumber and electrician each come twice?
The first visit is rough-in, when lines and circuits go into open walls and the layout is no longer adjustable. The second is after cabinets and countertops, for final connections to the sink, appliances, lights and outlets.
What is the order of trades in a kitchen remodel?
Design, permits, demolition, rough-in, drywall and paint, flooring, cabinets, countertops, then final connections and trim. Tile usually goes down before cabinets.
How long does a kitchen remodel take?
Block says a full kitchen remodel averages 6 to 12 weeks once construction starts.